Pressure vessel and compressor inspection report – template (PDF) for the qualified person
Report for periodic inspections of compressed air vessels and compressors by a person qualified to carry out inspections: plant data with pressure, volume and pressure-volume product, 23 check points from the documents via safety valve and pressure gauge to the condensate drain, defect list and next inspection dates.
As of PDFAMS Go editorial team
Free: sign up for the newsletter once and all templates are unlocked in this browser. You can unsubscribe at any time.
The pressure vessels of compressors are under pressure and age through corrosion – often from the inside, because condensate collects. The German Ordinance on Industrial Safety and Health (BetrSichV) therefore treats pressure vessel installations as installations subject to monitoring: they are inspected before commissioning and periodically, as a general rule by an approved inspection body (ZÜS). A person qualified to carry out inspections (zur Prüfung befähigte Person) may only inspect where the tables in Annex 2 Section 4 provide for this given the pressure, volume and fluid of the vessel.
The template is intended for exactly these inspections by the qualified person. It records the data that determine who inspects, guides you through documents, external condition, safety valve, pressure gauge, pressure switch, condensate drain and compressor, and records defects, the result and the next inspection dates. The record thus contains the details required by Section 17 BetrSichV. Before using it for the first time, clarify whether your vessel may be inspected by a qualified person at all.
What the template contains
- PDF report with plant data: compressor, pressure vessel, maximum allowable pressure, volume, pressure-volume product and fluid
- Fields for who inspects, type of inspection and basis of inspection
- 23 check points in four groups rated “OK”, “Defect” or “N/A”: documents, external condition, safety devices, compressor
- Fields for internal inspection and strength test, defect list with action, person responsible and deadline
- Result, next inspection dates per type of inspection and signatures of the qualified person and the operator
How to use the template
- 1
Clarify who inspects
Read the maximum allowable pressure PS and the volume V from the nameplate and calculate the pressure-volume product. With these values and the fluid, use the tables in Annex 2 Section 4 BetrSichV to determine whether a qualified person or the ZÜS inspects, and record this in the risk assessment.
- 2
Have the inspection carried out
The qualified person works through the check points on the vessel and the compressor, ticks “N/A” for devices that are not fitted and enters the findings of the internal inspection and the strength test where they are part of the inspection. Defects go into the defect list with component and rating.
- 3
Remedy defects and set dates
Have safety-relevant defects remedied without delay; if that is not possible straight away, the plant stays out of service. File the record at the place of operation and enter the next inspection dates with month and year in the inspection register.
Legal basis
- Sections 15 and 16 of the Ordinance on Industrial Safety and Health (BetrSichV): inspection of installations subject to monitoring before commissioning, after modifications requiring inspection and periodically
- Annex 2 Section 4 BetrSichV: pressure installations – inspection content, intervals and allocation between ZÜS and qualified person (Nos. 5 to 7)
- Annex 2 Section 4 No. 3 BetrSichV: requirements for qualified persons for pressure installations, including at least one year's experience
- Section 17 (1) BetrSichV: content of inspection records and keeping them at the place of operation for the entire period of use
- Section 14 BetrSichV: inspection of work equipment not covered by the inspections under Sections 15 and 16
- TRBS 1201 Part 2 “Inspections and checks for hazards from steam and pressure”
Frequently asked questions
Who may inspect the pressure vessel of a compressor?
As a general rule the approved inspection body (ZÜS). A person qualified to carry out inspections may inspect if the tables in Annex 2 Section 4 Nos. 6 and 7 BetrSichV provide for this for the vessel – depending on pressure, volume, pressure-volume product and fluid. For some vessels the ZÜS inspects before commissioning and the qualified person periodically. For pressure installations the qualified person needs, among other things, a relevant technical qualification, knowledge of the rules and at least one year's experience with such installations (Annex 2 Section 4 No. 3).
How often must a pressure vessel be inspected?
The employer sets the inspection interval in the risk assessment, for pressure installations no later than six months after commissioning. For parts that a qualified person may inspect periodically, the interval must not exceed ten years (Annex 2 Section 4 No. 5.9 BetrSichV). For pressure vessels inspected by the ZÜS, maximum intervals of two years for the external inspection, five years for the internal inspection and ten years for the strength test apply (No. 5.8). Manufacturer's information and the condition of the vessel may require shorter intervals.
What does the periodic inspection cover?
It establishes whether the necessary documents are available and plausible, whether the installation is in proper condition and can be used safely, and whether the technical and organisational measures are suitable (Annex 2 Section 4 No. 5.2 BetrSichV). The inspections of the parts consist of external inspections, internal inspections and strength tests. The external inspection may be omitted for pressure vessels unless they are fired, heated by exhaust gas or electrically heated, and for simple pressure vessels (Nos. 5.5 and 5.6).
You may use and adapt the template freely in your own company and for your own clients. It reflects the regulations named as they stand.
Never search a spreadsheet for a deadline again
In AMS Go, what this template covers lives in one system with reminders, history and records at the push of a button – mobile and with AI support.
Related guides
- Testing duties
Inspecting pressure vessels and compressors in Germany: intervals, ZÜS and qualified person
9 minRead - Testing duties
Installations subject to monitoring in Germany: inspection duties and approved bodies
7 minRead - Testing duties
Qualified person for inspections under TRBS 1203 in Germany: requirements, duties and appointment
6 minRead - Testing duties
Inspection intervals table: German inspection deadlines for work equipment and installations
9 minRead
More templates
- Testing duties
Work equipment inspection register template (Excel) with inspection intervals
ExcelFree download - Testing duties
Fall protection PPE inspection: checklist and inspection record (PDF & Excel) for the competent person
PDF + Word + ExcelFree download - Testing duties
Forklift annual inspection report template (PDF) for industrial trucks
PDFFree download - Testing duties
Crane inspection report template (PDF & Excel) with register for lifting accessories
PDF + ExcelFree download